Huaneng Yueyang Power Plant Focusing on Environmental Protection—China’s 1st
     

  On May 30, 2006, generator set #4 of Huaneng Yueyang Power Plant passed a 168-hour trial run and 

  formally started production concurrently with the desulphurization device. This is the first time in China 

  that desulphurization device is put into operation simultaneously with a new generator set.

   

  The phase 2 expansion project of the plant calls for the construction of 2 coal-fired generator sets of 

  300,000 KW. The construction started in April 2004, involving a total investment of 2.47 billion Yuan. 

  Generator set #3 was already put into operation in February this year. After generator set #4 was put into 

  operation, the plant had an installed capacity of 1.325 million KW to become the largest thermal power 

  plant already put into operation in Hunan Province.

   

  Generator set #4 took only 10 days plus 10 hours to complete the 168 hour trial run, and to be connected 

  with the power grid setting a record in the domestic power sector. It has also become the first in China to 

  put the desulphurization device and the generator set into operation simultaneously, marking a big step 

  taken toward the goal of building a saving and environmentally-sound thermal power plant.

   

 
 
 