Operation of First Biomass unit of China Huaneng Group
             

  At 16:18 on September 21, 2009, the first biomass unit of China Huaneng Group——unit 1 of Huaneng 

  Changchun Biomass Thermal Power Plant passed the 72-hour test run with high quality and was put into operation.

   

  Huaneng Changchun Biomass Thermal Power Plant is the first demonstration project of China Huaneng 

  Group for biomass power generation and was built by Huaneng Jilin Corporation. Located in Shuangyang 

  District of Changchun, it has 2 cogeneration units of 15MW each. Construction started on June 27, 2008.

   

  The plant mainly uses the straws of farm products as fuel, achieving remarkable economic and social 

  benefits. The energy utilization efficiency reached nearly 90%. The purchase of straws alone can provide 

  local farmers with nearly 50 million Yuan of income each year and all the ashes resulting from burnt straws 

  will be returned to the farmers for use as a fertilizer. After being completed and put into operation, the plant 

  is expected to process some 200,000 tons of straws, save 85,000 tons of standard coal, generate 180 million 

  KWH of electricity, achieve an output value of 108 million Yuan and over 15 million Yuan of profit,and 

  taxes each year, provide over 200 jobs for local farmers.

 
 
 